18 weeks behind the original programme and 12 weeks behind in volume terms
Sponge Bob wrote: » 18 feb 2010 My prediction on an opening date is the second half of October 2010.
Sponge Bob wrote: » I estimate the precise opening date will be Friday the 22nd of October this year but Chris has the doubling dice till the Galway Races
Senior engineer with Clare County Council, Tom Tiernan, told a recent meeting that the council has been told that the works could be complete this autumn.
tech2 wrote: » Good progress, it might tempt me to go up and have a look at the scheme on Sunday. Ascii how is the Rathwilladoon overbridge going, last time I had a look the decks were up and structure was in place. No embankment done on it however. Just that one and the Cragard one to complete.
ki wrote: » Thanks glineli You seem to be the only one flying the flag for updates at the moment.
Nath wrote: » Ballybaun to Curtaun Lurga Underpass Shangalish Overbridge Gort - Tubber OverbridgeGort to Ballybaun Ballysheedy Underpass R460 Overbridge Gort Junction