DMARTINGTI wrote: » Steel frame structure arrived 2 weeks ago. Really starting to see progress now. Guys should be finished in a few days on the frame. Great to get going after so many rain delays.
DMARTINGTI wrote: » We've got the building structure up now and the outside is clad in 14mm cement fiber board. Just wondering if anyone has any had any suggestions for the external finish. The current suggestions are to put an outer leaf of concrete blocks with a 100mm cavity filled with rockwool cavity insulation. Or blocks and filled cavity up to the downstairs window sills then suspend 100mm polystyrene on batons to make a cavity then plaster onto the outside of this. Either way on the internal frame we have 140mm so this will be filled probably with rockwool then plasterboard or softboard. Any thoughts or suggestions?
thekooman wrote: » built in mayo Seamus. 3200 sq ft house & 800 sq ft garage. sent a PM with some details of prices.
RKQ wrote: » Veneer is "usually" MDF. They can't be sanded or easily repaired if they are chipped or scuffed. Skirtingboards are meant to protect the wall from knocks and bangs. Veneer is fine in low traffic areas. The oak veneer I looked at wasn't hugely cheaper than solid oak. Veneer shirting comes in limited moulded designs. Solid oak is expensive but its worth getting 3 quotes from local Joinery's. Solid oak will be cut to the size and design you want. Solid oak can be sanded in the future, if required. All doors, skirtings and architrave tend to get knocked and banged during normal life. Soild oak can be screwed and plugged (oak plugs cover the screws, so they are hidden!):)
Jill wrote: » Thanks for this - can you get the solid oak finished or will we have to do that ourselves ?
whitelightrider wrote: » Hi Jill, we got 650ft of skirting and architrave in solid oak for our house from a local guy. He sprayed the whole lot for €600. Far easier than sanding and sealing the whole lot.
DustyBin wrote: » Hi all We've recently got our planning and will hopefully be clearing site before Christmas Will keep you posted on how things are going and will surely be looking for lots of advice! In the process of deciding how to manage the build but looks like we will hire a project manager and do it all direct labour through the PM Has anyone any idea how much a project manager should be charging? We want them to supervise from digging of foundations through to 2nd fix electrical, plumbing & carpentry Thanks for any advice you can give
wondering... wrote: » Hope the foundations got poured DustyBin. Just wondering if you had more information on how the PM situation worked out. Am currently looking at getting a builder, but wouldnt mind checking how a PM role would work. I'm begining to shy away from the direct labour approach as I dont have a lot of building knowledge. Is getting a PM a good half-way house - or am I better off sticking with a builder? I wouldnt mind getting my hands dirty with the build, but dont want to end up with very expensive mess either
Tester46 wrote: » Hi - did you get the skirting and get it sprayed for an all in price of €650? Whereabouts?
getfit wrote: » The PM road is a very grey area... That's why prices are so variable. Basically, do you want the PM on site 20/30 hours a week to supervise work and co-ordinate deliveries, hire work men and make decisions!! Or, do you want the PM to just throw his eye on things and make sure no mistakes are made which could mean no hours on site some weeks and 5-10 hours on site in busy weeks...
bauderline wrote: » Its been a while... but some updated photos on the blog...http://watergate-house.blogspot.com/