Hi lads/ladettes. Sorry, this is a bit long, but stick with me for a minute.
I've been slowly upgrading electrics as finances allow and as I switch to renewables. My house is a late 70s build. Had no issues with electrics, but needed a new CU as the old one was a mess and had to have a separate mini board added a few years ago for EV/Shower isolator. This is before load sensing was commonplace.
I had 5kW of Solar installed in March. As part of the install, I negotiated an all-in-one package with the solar company to have their electricians (contractors) upgrade my CU and tails to allow for a 100A ESB main fuse.
What I had:
8kVa supply (only recently discovered)
10mm^2 tails and a mess of a CU from the mid 90s with a tacked on priority board from the shower/EV.
I got an earth rod and bonding done last year to prepare for solar.
What I wanted:
25mm^2 tails (16mm^2 earth) for 100A ESB main fuse upgrade.
New CU with extra space for planned additional capacity.
What I got:
25mm^2 tails as requested. They put an 80A breaker/(isolator?) into the meter cabinet.
A new CU, but as they combined it with the older split unit housing the shower/EV priority switch, I didn't end up with much space for spares. Probably enough space for 4 spares. I also just checked after reading this 12kVa to 16kVa thread and the CU says it's rated 63A.
I also have a pending free upgrade from 8kVa to 16kVa from ESB, who have installed an 80A fuse in the meter. The ESB electrician said he should only be putting a 60A fuse, but put in an 80A when I explained the scope of the works.
Overall, I am happy with the work, but seeing the 63A on the CU is a bit of a dampener. I don't know if the busbars are also only 63A rated. Not sure what steps to take.
We are high users. 15k units consumed last year. Dublin suburbs. Lots of us in the house. 2 EVs, Solar, 30kWh storage and we hoover up as much electricity as possible on the cheap 2-6am rate with Energia to reduce the bills. Our heating is Gas and our hob is gas. Although we use very little gas (€600 in 2023) I would like to get rid of our gas boiler and move to a HP if possible.
My 2-3 year Plan:
Get my supply upgraded to 16kVa. I wonder if it's worth asking ESB about doing this before they install the 12kVa and would there be a reduction in the normal cost of upgrade if they do this when they would be doing the 12kVa anyway?? My supply is looped to my neighbours…if that makes any difference.
Get my 5kW Hybrid inverter upgrade to 8 or 12kW to accommodate for faster battery charge/discharge rates, also reducing/eliminating any draw from the grid outside of the cheap rate.
Install another 5kW of solar on my shed and extension, most likely using N-Phase micro inverters. This will involve a leccy installing a mini CU in the shed. I already have a spare 32A in the main CU to feed into.
What way would you go about it? The outstanding issues are the possibly limited CU to 63A and the currently 8kVa…hopefully soon to be 12kVa or maybe even 16kVa supply, depending on cost.
The old CU and priority switch unit.
The new CU
Meter box prior to ESB connecting tails