I'm in the process of building a house and just starting the application process to Irish Water to have our services connected.
Their site mentions that it can take 16 weeks to have a connection agreement finalised and then 12 weeks from when the road opening license is secured.
Does anyone have any experience on how realistic these timelines are?
Would be great if it was quicker but I've heard storied that this part of the process can take a significant amount of time.
I'm building on a site that already had a house there previously so that might speed up the process if pipes are already in place?