The Parrot wrote: » Need some advice. Planning permission for my plot runs out in june 2013 has been extended once before by the previous owner.we will be able to get the house to roof level by then but not finished, can we get the planning extended again , i have been reading the planning and development act 2010 and it seems some what contradictor. if the planning was extended before the act was put in place im ok. but if not i think its a grey area. i already asked this in the planning thread but i think it was just over looked so im asking again for advice here. thanks for any help
A Country Voice wrote: » If you send in your commencement notice now and get it up to roof level before the expiry date, ie "substantial completion" then you wouldnt need an extension. Financial or other matters might not allow this maybe? It seems the safest bet to me to get it up to the wallplate and then you dont need to worry about the planning permission running out. ACV
Poor Uncle Tom wrote: » The problem then is that the planning permission would have expired and the works are not completed. By virtue of this fact what works are carried out on the site become an unauthorised development by default and carries all the enforcement implications that go with it. You then need to apply for retention of what is on the site and get planning to complete works.
A Country Voice wrote: » In my opinion thats not correct Tom. If works are substantially complete, (most PA's in my experience put the minimum requirement of substantial completion to be that the walls are up to the wallplate), prior to the expiry date of the planning permission then no retention permission is required. If the developer's architect/engineer signs off on it being substantially complete before the expiry date of the planning permission then there shouldn't be a problem. I would of course check with the Local PA to see what their take on "substantial completion" is before taking this course of action though. ACV
Poor Uncle Tom wrote: » I'll get you a reference for a recent ruling, October just gone, if memory serves.
A Country Voice wrote: » ie getting the house built to wallplate level prior to expiry and then being free to complete afterwards
muffler wrote: » Good luck with that
A Country Voice wrote: » get it up to roof level before the expiry date, ie "substantial completion" then you wouldnt need an extension............ to get it up to the wallplate and then you dont need to worry about the planning permission running out.
A Country Voice wrote: » the walls are up to the wallplate), prior to the expiry date of the planning permission then no retention permission is required.
A Country Voice wrote: » Have you got more info to share with the rest of us?
The Parrot wrote: » bBut if anyone can find another planing directive that can help please do but im not having any luck. i have even been talking to the council. which were very helpful. shockingly
A Country Voice wrote: » It would affect a lot of projects which have been slowed down by the economy if substantial completion was no longer valid, (ie getting the house built to wallplate level prior to expiry and then being free to complete afterwards).
A Country Voice wrote: » If you send in your commencement notice now and get it up to roof level before the expiry date, ie "substantial completion" then you wouldnt need an extension. Financial or other matters might not allow this maybe? It seems the safest bet to me to get it up to the wallplate and then you dont need to worry about the planning permission running out.
Poor Uncle Tom wrote: » That was always my understanding of it as well, and technically you can still do that if the works don't stop. So if I start building my house with say 4 months left on the planning permission and I reach 'substantially completed' stage by the expiry of the permission I can still go ahead and complete the house within a reasonable period. That's even mentioned in the planning act. N
The Parrot wrote: » given me even more to think about. can you let me know which section of the planning act relates to this.?
Poor Uncle Tom wrote: » Just coming back on this. It was a clarification issue I had with a Local Authority which was cleared up by DOS in October for me. It had a direct bearing on 3 separate planning applications I was working on (all of which have worked out successfully in the meantime) and basically went as explained below. That was always my understanding of it as well, and technically you can still do that if the works don't stop. So if I start building my house with say 4 months left on the planning permission and I reach 'substantially completed' stage by the expiry of the permission I can still go ahead and complete the house within a reasonable period. That's even mentioned in the planning act. The problem we have today with most sites, and I think in this case as well, is that there would be an amount of work carried out, say to 'substantial completion' stage and then works would stop as funds would probably have run out and the site would be left like that until further funds were available to do more. In that case, when works stop on the site and where planning permission has expired, since the works on site are not completed, whatever has been done is considered to be an unauthorised development by default and works cannot re-commence without a new planning permission (retention and completion) being put in place. There are a few points worth noting and each of the LA's I've checked this with have said the same. 1. The planning departments themselves are not going around checking all sites and have no idea which sites are stopped work. 2. Having the house at substantial completion stage by the expiry of the planning permission means the planners will do all they can to help you secure the new planning permission (they won't refuse permissions out of hand) but there are no guarantees. 3. If the 'works stopped' situation comes to the attention of the planning department via complaint from a third party, the applicant will probably be dealing with an Enforcement Notice as well as a retention and completion planning permission application. I hope that explains it and I'm sorry for any confusion but I assumed from your post that you were implying that works could stop once you reach substantial completion stage and that you would not need any planning permission to start up building works again. But of course you do. Now I know if we didn't have our forum charter we could say things like, "sur the council will never know if I stop works for a year" but we can't say that here. It would not be an acceptable risk to take in any event. Also there are the implications if you go to sell, or if there is a forced sale, at 'substantial completion' stage where the planning permission has expired.
Did anybody every get a definition of substantial completion or is there any ABP or legal case reference?
Thanks.
good info here
https://www.boards.ie/discussion/2055722227/definition-of-substantially-completed
Thanks so much.
It would seem to be external blockwork and no more.