My relative is having 100mm external insulation installed under seai. Replacement footpaths, new door, ramp, steps and rail to be installed under a different scheme. Which order would they need to be done in, or does it matter. I was thinking new door may need to go in first, then ewi, then replacement footpaths (mainly due to gully's, etc moving out 100mm) , ramps, steps, rails?
Note. It was confirmed that the ewi contractor will install to the level of the existing footpath only, which I believe is the standard practice in almost all cases.