IE 222 wrote: » Another potential issue that could arise unexpectedly now is from Rosslare users and understandably. Although Dart South isn't for another few years the details would suggest changes to Rosslare will need to be implemented with Maynooth as that requires terminating on platform 7. Connolly will effectively only have 2 through platforms, 5&6. I'm not sure it running them through is an option but terminating definitely won't be.
MJohnston wrote: » Given that Leo Varadkar has seen fit to interfere due to this bridge, it seems like it might become a fairly critical part of the project.
liamog wrote: » The houses at the front of Riverwood are about 7m away from the main road, so it would seem this shouldn't really be an issue. The embankment leading up to the bridge in Stationcourt will be about 20m away from a retaining wall and the report does also mention than noise abatement measures will be required across the new bridge. It's better to work constructively to improve the options instead of some of the local claims which are demonstrably untrue.
CatInABox wrote: » Wouldn't be surprised to see the Rosslare trains terminate out in Bray/Greystones, and passengers transfer to a waiting Dart. In fact, did I read something about this recently? I'll have a look, because I'm sure that I saw mention of this recently. Perhaps it was just the Wexford trains?
IE 222 wrote: » It's better for the tax payer as well to accept their claims and leave them with only a footbridge. To be honest I see their objections as a free pass here and to be jumped on at the earliest opportunity. Any inconvenience or hardship in the area as a result of this is completely self inflicted by the locals. The only ones I feel sorry for are the locals who support and want the bridge that won't get a chance to have their voices heard as their views have already been drown out by this biased residents association mandate.
riddlinrussell wrote: » Given that Connolly will be worked on as part of the 'last' piece of the puzzle are they possibly getting the rest of the system to shovel ready and then hoping to present the more comprehensive rework as a fait-accompli to avoid wasting all the money already spent?
liamog wrote: » The main problem is that you can probably draw a circle for the objections, consultation 1 results in a "win" for the small number of residents who will get to maintain their field, consultation 2 see's the residents who currently live south of the railway up in arms because they are now further cut off from the greater d15 area.
IE 222 wrote: » That's exactly what's going to happen and that's why I'm bringing it up as it would be viewed as a bit of an outsider in terms of Dart West and would come unexpectedly for many. To be fair they'd be more inconvenienced that Coolmine folks imo.
CatInABox wrote: » Yeah, found what I was looking for alright.Annex-3-4A-Appendix-A-Peak-Hour-Service-Plans This is just peak hour I suppose, so perhaps they'll have Connolly to Rosslare running at other hours, but to be honest, I can't see it happening. Once they make the swap for the peak hour, they'll hail it as a success and run it from there all the time I'd say. There's some other stuff in there as well, such as Howth Junction to Howth becoming a shuttle service.
IE 222 wrote: » Dundalk and M3 will also be shuttle.
D15er wrote: » However, when they bring forward the proposals for Castleknock, expect sparks to fly there too.
CatInABox wrote: » Not during the peak hour anyway.
IE 222 wrote: » Is option 6 not been implemented. It would agree paths diagrams.
MJohnston wrote: » Why would they need to bring forward proposals for Castleknock? You mean the bridge demolition and modified rebuild?
D15er wrote: » It's a protected structure so demolition is problematic to say the least. There's no room to widen the span of the bridge either, at least not on the north side. I'm sure there's an answer but it's just odd to be talking about filing a railway order in Q2 2021 when major challenges are either unresolved or the solutions haven't gone for consultation.
MJohnston wrote: » It’s not a protected bridge according to the Full Report (there’s a section on bridges, and protected bridges are flagged). I think the one that crosses the canal is protected, but maybe not the railway bridge.
D15er wrote: » It's the same bridge, there are two arches - one over the railway, one over the canal, but it's a single bridge. You're actually correct that the IE report says that it's not a listed structure - but that is wrong, it is protected.
IE 222 wrote: » Are you referring to the road bridge at Castleknock station?? These are 2 separate bridges. The rail bridges are not listed. The canal bridge is listed. The platforms won't allow a lowering of the track bed. The bridge will most likely be raised and a flat deck installed similar to the Old Navan Rd bridge. That bridge will most likely be raised as well. Broombridge could be knocked and incorporate something into the new Luas bridge.
Pete_Cavan wrote: » Will having the depot west of Maynooth have any negative impacts operationally? I mean, how will drivers start/end their shifts with the depot west of Maynooth? The first drivers of the day drive to the depot and train departs from there, how do they get back their to head home if the train doesn't return to the depot until the end of the day? Would it be better to have the trains passing the depot in service allowing for change of driver plus facilities for breaks, toilet stops, etc all at one location?
L1011 wrote: » We already cope with depots in Portlaoise and Drogheda for services that start a lot further in. There will not be any depot on the Hazelhatch service, so trying to think of idealised service patterns to reduce dead running by either vehicles or staff goes out the window.
Pete_Cavan wrote: » Presumably the relevant trains are regularly returning to those depots in service throughout the day.
MJohnston wrote: » Broombridge should 100% never be knocked.
Pete_Cavan wrote: » Presumably the relevant trains are regularly returning to those depots in service throughout the day, meaning they don't have this same issue. I was thinking more about extending DART to Kilcock, thereby passing the depot. It may be idealised but it is also beneficial for very little extra cost/effort. Surely the point of this type of investment is to make operations as efficient as possible. HH may not have a full depot but some documents definitely referred to stabling there.
IE 222 wrote: » They'll need to alter it one way or another. The fact a new bridge is been built for Luas at the exact location it would be rather simple to do them both as one unless there is something preventing Broombridge been demolished.
MJohnston wrote: » Broombridge might be specially modified as per the Main Report, but it’s a truly historic bridge, beyond even just being protected. [img][/img]https://www.boards.ie/vbulletin/attachment.php?attachmentid=528814&d=1602277777