cillo2000 wrote: » That's some sight, thanks Marno. How much time do people estimate it will save at off-peak times? 10-15 Minutes?
marno21 wrote: » As someone in the same boat, would highly recommend taking the Mill Road around Macroom if you don’t already. Some serious amount of work going on down there. Absolutely transformative scheme for the Cork-Killarney journey.
hans aus dtschl wrote: » Yep been watching from that perspective, very dramatic. Progress is very visible on lots of stretches around the main Ballyvourney route too. I think the saving will be more than 10-15mins. It'll save me 10-15mins on a normal day. Peak time (bad days) it could save me 20-25mins. Pretty significant.
marno21 wrote: » The Macroom part is the biggest priority.....
marno21 wrote: » Some even more up to date drone footage
marno21 wrote: » https://www.youtube.com/watch?v=VPBe5mLxZOM Some even more up to date drone footage
Apogee wrote: » I think that footage shows the new road intersecting with the N22 at 6m25s. Which corresponds to this location:https://www.google.com/maps/place/Sleveen+East,+Macroom,+Co.+Cork/@51.9117982,-9.0244467,264m/data=!3m1!1e3!4m5!3m4!1s0x4844e44c4c6d2a55:0xa00c7a997319de0!8m2!3d51.9048039!4d-8.9588478 How likely is it that we might see an early opening of the Macroom by-pass reconnecting with the N22 here?
Quackster wrote: » Extremely likely.
marno21 wrote: » Opening the section from Coolcower to Carrigaphooca is very feasible and would do wonders for traffic in the area.
cantalach wrote: » I would love that to happen but, as I said when this came up before on this thread, that might not be legal from a planning perspective. I know that sections of new road elsewhere in the country have opened early before. But the difference in this case is that the fully completed new road will not have any junction with the old N22 at that point. So they would essentially be creating a new junction without any planning permission. Perhaps its temporary nature would make a difference. Who knows. Another issue is that if the contract doesn’t place any requirement on the contractor to do this temporary tie-in, and if it doesn’t offer any kind of bonus incentive to do it, why would the contractor bother doing it? It’s a business in the end of the day and few businesses spend money just to be nice.
marno21 wrote: » https://www.youtube.com/watch?v=Hbtyl6zmrng Fantastic video from the contractors showing how the proposed Bohill bridge near Ballyvourney will be constructed. Timeline and full construction sequence shown. It highlights yet again how high the specification of this scheme is. If this was built 20 years ago it'd be an at grade single carriageway. Compare that with this.
rounders wrote: » Very impressive! Thanks for sharing! EDIT: Also impressive to see they made a Irish language version too!
cork_south wrote: » Seems that video is private now
Update on the Coolyhane Underbridge As anyone living in the Ummera, Coolyhane or Masseytown knows, there has been significant progress with the construction of the Coolyhane Underbridge over recent months. This structure is the most advanced of the 130 structures included in the overall contract and is progressing well at this point. The recent closure of the Coolyhane Road (Mill Road) was necessary to facilitate the construction of this bridge and it is gratifying to see it taking shape. The new N22 road will pass over this bridge and the Coolyhane Road (Mill Road) itself will be realigned to pass underneath. These photos show recent construction works on the bridge. The first precast concrete beams for the job were dropped into position on Thursday 6th August. These beams are MY type units, supplied by Banagher Precast in Co Offaly. The beams themselves are approx. 9m long and weighing 4 Tons per unit. These beams were placed onto the concrete walls recently constructed by the contractor’s site team. The concrete deck for the new carriageway will be cast over these units in the coming weeks. The contractor has applied for another Temporary Road Closure of the Coolyhane Road (Mill Road) for a 5 week period commencing on Mon 7th September. If approved, this road closure will permit the contractor to construct the realignment of the Coolyhane Road (Mill Road) so that it will run under the new bridge and that will bring this element of the project to a conclusion. Finally, the contractor would like to thank the residents of Masseytown, Coolyhane, Firville and Ummera for their co-operation with the original road closure and hopefully the work can be finished on schedule so as to keep the local impact to a minimum.
Water John wrote: » Yeah the Mill Rd closed today. Vehicle breakdown on Castle St around pm. Queue to 2 mile bridge, incl 4 Christy Lucey trucks with wide loads, absolute nightmare.
aisling86 wrote: » Absolute mayhem again this morning. Traffic all the way back up masseytown.
N22BBM wrote: The contractor has applied for another Temporary Road Closure of the Coolyhane Road (Mill Road) for a 5 week period commencing on Mon 7th September. If approved, this road closure will permit the contractor to construct the realignment of the Coolyhane Road (Mill Road) so that it will run under the new bridge and that will bring this element of the project to a conclusion.
serfboard wrote: » Well, better get used to it because ...
aisling86 wrote: » Yup fully aware. With 130 structures going in, it will be a long few years but it will be fabulous when it's done. There is talk locally that that macroom section could open by next summer.