BArra wrote: » if the NBP gets the go ahead, would Eir be allowed to suddenly decide to expand their rural rollout?
Emmanuel Lemon Louse wrote: » Not wishing to re-start any arguments but last night I implied Marlow was involved in the claim by ISPs of premises in the intervention area. Marlow assures me this is not the case so I, unreservedly, apologise for my comments and withdraw them.
ctlsleh wrote: » Fair play......in my opinion Marlow provides really good insight on this forum and has always been considered, reasonable, fair and on the side of the subscriber throughout
KOR101 wrote: » At the time the pole rental was set at €20 it was never envisaged that there would be wholesale use of the poles. Comreg will have to revisit this if the contract is signed and commission a new economic analysis.
user1842 wrote: » So if the contract is signed will the GMC have to wait until EIR replace all the ageing/broken telephone poles in the country? Im sure EIR will not be in any hurry to do this and thus the roll-out will take a lot longer.
Emmanuel Lemon Louse wrote: » It would cut into the rental as it is calculated on the amount of cables per pole. However I think we have seen from their intervention where they claimed that they could complete the project for less than NBI, that the rental money is not that important to them. I'm not even sure that they make that much on it.
Grab All Association wrote: » There’s a pole outside Borrisoleigh that split in two at the start of the year. Despite reporting it to them a number of times, still not replaced. The fibre is keeping it hitting the ground. Old telegraph pole. None of the poles were replaced.
The Cush wrote: » Why would they have to, GMC would have submitted their bid based on the current shared regulated access price to poles, ducts etc.?
ArrBee wrote: » How do you mean per cable, and what constitutes a cable in this case? Like per strand or outer cable? My point was that if the NBP goes ahead, I am guessing the map will be locked in and be built towards. An operator (such as Eir) coming in and increase their network inside of the intervention area would not change the build plan hence the NBI cable will still run everywhere it was destined to at the start and the rental will be the same. Sure, there will be these "compensation payments" what are in the contract for having another provider poaching houses during the build, but I don't see how the build project can be so dynamic that it changes the rental on poles based on competitor build outs. If I have the above correct, then I'd also be interested to know if NBI will be allowed to compete in areas that are intervention areas at the start of the build but become serviced commercially before NBI get there.??? Hopefully for the sake of the "process" once the IA is locked down and contracts are signed, the NBP can not shrink.
KOR101 wrote: » I wonder whether the contract allows for changes in that. I can see why GMC might not care, but the taxpayer does care.
Emmanuel Lemon Louse wrote: » The outer cable. So if there is an NBI fibre cable on the pole plus an open eir copper cable the pole rental cost is 50% each. If open eir then add their fibre cable they pay 66% of rental etc. Any savings made by NBI in build costs will be subject to claw back mechanisms for the Government. As to your second point I assume once the intervention area is locked down, which this recent mapping consultation was meant to achieve, NBI would intend passing all of those premises no matter what. I don't believe the IA can shrink. Obviously open eir could still build in some of those areas but there has been no indication that they will.
ArrBee wrote: » OK, I get you now. They would have to weigh up the loss in pole rental vs the lose of revenue from connection fees they would be allowed to charge every time a customer changes provider. I wonder if Eir will offer services on NBI infrastructure....?
Emmanuel Lemon Louse wrote: » If they don't extend their own build I believe they definitely will. They could hardly ignore 540000 potential customers.
KOR101 wrote: » Dáil debates Tuesday, 12 November 2019 Brendan HowlinThe Minister for Communications, Climate Action and Environment, Deputy Bruton, has been forced yet again to deny that there has been another delay to the national broadband plan. Last week, I reminded the House that a private operator, Imagine, had warned as early as February, before the Government signed off on the plan, that this could lead to difficulties with EU state aid approval. It has now emerged that the Regional Internet Service Providers Association, the industry body which represents smaller rural wireless operators, is also considering taking a legal challenge to the plan on state aid grounds. There is real uncertainty now at the 11th hour. Can the Taoiseach clarify if the current delay is due to the objection to the Government's application of EU state aid rules and, if so, what is the potential cost to the taxpayer if this challenge is successful? Can the preferred bidder, Granahan McCourt, apply for additional compensation from Government for encroachment by other operators of high-speed broadband before deployment of the plan? Leo VaradkarThis matter is with the European Commission at the moment. The Commission is assessing our submission in favour of state aid being granted for this project and any other observations that are made by any third parties on whose behalf I cannot speak. That is being assessed by the European Commission as we speak and we will, hopefully, have a positive announcement with regard to state aid clearance in the next couple of weeks. It is, of course, open to anyone to take a legal challenge and that is why I counsel people who think that an alternative to the national broadband plan could be done less expensively and more quickly. This process has taken a long time. It was a detailed procurement process that was open to challenge all the way. We should not be under any illusions that if we do not go ahead with the national broadband plan, it will mean going back to square one, which will delay this project by three to five years.
allanpkr wrote: » in my opinion this is good, let the process be above board and clear. if after all due diligence the eu pass state aid, i dont see any legal process that rispa and imagine would consider anything but a costly waste of money.
clohamon wrote: » If the challenger is still unhappy, then it's off to the CJEU to challenge the Commission's approval decision.
user1842 wrote: » And by the time that happens, the network will have been built
In order to demonstrate the current state of play, and provide evidence of the private investment already made, 28 Irish WISPs joined together to undertake a detailed analysis of their current broadband coverage. For this purpose, mast data, including location, height and current capability and operating frequency details (i.e. NGA-capable or planned for upgrade to NGA capability) for 1,700 tower sites was supplied to Leeds based Wireless Coverage Ltd.
Following the analysis by Wireless Coverage it was determined that there are currently around 1.5 million properties that could be served by existing operators to a basic level i.e. either NGA or non-NGA compliant. Of these residential and business locations, nearly 690,000 are already NGA-compliant (i.e. 30 Mbps or higher) and around 84,000 premises are currently connected with service from one of the 28 contributing WISPs.
David Burns, founder of Wireless Coverage, Chairman of the UK Wireless Internet Service Providers Association (UKWISPA)
Traditional wireless planning systems take around 15 minutes to perform the calculations needed to produce a single viewshed, so for this particular project, that would equate nearly 150 hours once the data had been sourced and prepared,” says Burns, who adds, “Using WISDM all 1,700 viewsheds were completed in less than two seconds.
Gary kk wrote: » Which network?
clohamon wrote: » Interesting link to the propagation modelling carried out by the WISP consortium. Apparently already submitted to the Department. Claiming 28 WISPs in the consortium, 1700 sites, and 84,000 NGA compliant wireless customers (existing).https://twitter.com/gloverstweets/status/1194914249224704000
Emmanuel Lemon Louse wrote: » So the Irish WISP association has contracted the UK WISP association to kill the NBP. I can only hope that the DCCAE and EU make a mockery of their two second mapping.
clohamon wrote: » ...and a few more issues besides contention backhaul unlicensed spectrum informal site agreements