NRA have this morning advertised for engineering consultancy to design medium to long term solution to the junction!
:):)
Gunner3629 wrote: » The cost of the project may - possibly - be lower but the negative economic effect of further delays will also have a cost.
Pete_Cavan wrote: » The engineers on TII's side say the cost should be lower than what Sisk are quoting. Tendering amongst multiple contractors will almost certainly result in lower bids than negotiating with only one. The Children's Hospital was on site before costs spiralled so the option to retender wasn't there.
Gunner3629 wrote: » Who's the say that after re-tendering the cost will be any lower than what Sisk are quoting. Even thought Children's hospital is a much bigger cost to the taxpayer, and ultimately spiralled out of all control, why was this action never taken there?
prunudo wrote: » A lot of threads on here have start dates that long ago unfortunately, depressing state of affairs really.
Limerick74 wrote: » https://www.tii.ie/news/press-releases/dunkettle-interchange-update/
Odelay wrote: » Lol. Posted in April 2009
Drax wrote: » Excellent news indeed... expect it in around 10 years. :pac:
Gunner3629 wrote: » Could have a new government by then. Very frustrating.
Cork Trucker wrote: » What a fcuking joke, but not unexpectedhttps://twitter.com/JoeLeogue/status/1161940871086039040
tonc76 wrote: » Regarding the interpretation of the ground investigation results, testing has been ongoing throughout phase 2 of the tender so this is additional info that TII's engineers would not have had when estimating the scheme cost prior to the tender commencing. As a result couldn't it be possible that the estimate is off the mark as a result? With this form of contract as I understand it, the majority, and if not all, of the risk lies with the contractor so a premium will be paid regardless. Cost increases which are justified and verified, based on actual quantities and tendered rates would possibly offer better bang for your buck but the cost could also spiral if the original construction cost estimate was off the mark. I'd hate to see the project delayed and retendered as it is badly needed. If it does happen though it would be interesting to see the difference in construction cost between the "new" phase and the cost that TII and sisk are supposedly negotiating over at the moment.
Pete_Cavan wrote: » Much of the results of the ground investigation comes down to interpretation, two engineers could look at a borehole log and make a case for two very different solutions needed. If the engineers on TII's side do not agree with the conclusions drawn by the engineers on Sisk's side, this process should be scrapped. Sisk have nothing to lose here and will be looking to squeeze everything they can out of TII, who will suffer a lot of reputational damage and bad PR if the project doesn't go ahead. The cost that Sisk are due to submit may be the final but it will be inflated with premiums for risk. Costs not rising from the contract award sounds good but not if you are paying over the odds to begin with. Cost increases which are justified and verified, based on actual quantities and tendered rates are better than contract price jacked up before any work is done based on "what if".
SeanW wrote: » If it goes back to tender, is there anything to be gained by breaking the project up into chunks? For example, the slip road from the N8 East to the M8 North is mostly a re-use of an old road, I'd imagine these ground issues are less of a factor there or that this should be one of the easier parts. If the project is to be re-tendered, then could Sisk be told "go ahead and build that slip road, the rest will be re-tendered"? Or would the government have to tender that slip road as well? I ask because it seems like it might a quick-win to take some of the traffic off the roundabout, if the overall scheme gets delayed.
tonc76 wrote: » It appears to me that the ground investigation issued to tendering parties was not robust enough as GI that has been undertaken since has apparently shown the conditions to be much worse than anticipated. I may have missed this but was the cost that Sisk are currently talking about mentioned, other than the €160m or so figure mentioned by Micheal Martin a few weeks ago? Also the cost that Sisk are due to submit will be final cost whereas if procured under a different contract type there would be no certainty on final cost which on projects in years past amounted to massive additional cost.
Gunner3629 wrote: » They are worried about a few million when the Childrens hospital was 100's of millions over budget. If it was Dublin it would have been done a decade ago like the Red Cow and Newlands Cross. Just get it done.
Markcheese wrote: » Is it only a few million? I assume tii have a budget too.. I don't really buy the if it was Dublin thing.. There's projects in Dublin that are looking for cash too... (and I say that as someone who's often stuck on the the N40)
Jayuu wrote: » I guess the question is how much is the potential cost increase? Has there been any figure quoted?
Lackadaisical wrote: » Sounds like this will be cancelled then, having already screwed up the tree cover and landscaping around the junction too. Total mess.