Virtanen wrote: » What's was it like today merging from the M9 to the M7 with only one lane? Travelling to Dublin tomorrow afternoon but considering exiting at Kilcullen and rejoining on the other side of Naas to avoid most of the roadworks if the delay is very bad
harr wrote: » I know we don’t want to dwell on speed and speed cameras but anyone else notice it has gotten dangerous. I only travel on the M7 for a full week once a month but definitely have noticed a big increase in speeds. About half the drivers sticking to 60 while the rest are tipping along, twice this morning i seen lorry having to break hard and almost slam into cars doing the 60 ... particularly bad on the newly laid sections. I think drivers are now well aware where the speed vans can and cannot park so little chance of getting caught caught on certain sections. Always a van just before the M9 merger. ... ( south bound)
Emme wrote: » I had no problem sticking to under 60 this morning. I don't agree with exceeding the speed limit but I think a lot of motorists are sick of the length of time the road is taking to complete and the tens of km of enforced speed limit. It's one of the main roads out of Dublin and they are really taking their time with the upgrades. A lot of people are fed up with the slow progress and false promises of completion. It's looking like 2020 before it's going to be properly finished and more than likely we'll have to crawl along at 60kmph until then.
Eoghanj wrote: » The problem with this project is that it is not meeting expectations - which were set by Kildare county council when a representative came on national radio in January and said "there will be three lanes open in April". I heard the interview on Newstalk, and i was very surprised by it, as i travel from Carlow to Dublin every day and travel through the works. It does not matter at this stage what the original completion date was, as Kildare CC set a new date of April 2019 on the morning show on Newstalk. If they had not made that statement, there would be a lot less frustration, as the exception of an early opening would not have arisen. If the original date had been maintained in public debate, most of us would probably be happy with the progress being made. But now, every week that goes by is another week beyond the opening date set in January by Kildare.
rameire wrote: » false expectations from civil servants / councilors / politicians, nothing new. I think all that post here should realise by now that information was incorrect, no need to keep repeating it.
ronoc wrote: » Question for people doing this commute at rush hours. How much does the 60kmh limit add to your journey time compared to before the road works begun?
WishUWereHere wrote: » I only travel as far as J10 every working day, so cannot speak for any further. I cannot recall the last time I saw a Gatso van on the roadworks. I agree that people are back to going as fast as they can, but why not?. Aside from people knowing where the vans can/not park, the fencing is too high ( I think) for the Gatso to be able to capture the registration number.
[Deleted User] wrote: » Why are we revising such recent history? The expected completion dates were set by the contractors and relayed via public bodies.
rameire wrote: » yeah, cant believe they have been building it for 10 years. so annoying. they only started working on the road in October 2017, the contract is to have it all done by Jan 2020. it is a 27 month, 110 million contract.
MaceFace wrote: » While it is frustrating for everyone, the vast majority of posters, including me, have no understanding of the project. Suggesting that it is badly managed with time padded, or that it is behind schedule, or that people should have been working 24x7 last summer or in dark nights, or even that other countries "do it better".... well, what qualifies you to say such a thing?
_Kaiser_ wrote: » Ultimately, it's an extra lane and a bridge with some new/amended surrounding roads. It's not constructing the Empire State Building, and it's a project that is done all the time - indeed the nonsense PR video a while back with slow motion drone shots made much of the supposed expertise and experience of the companies involved. There can be no other reason for much of the road lying idle but segmented last year than bad management and padding. If that section wasn't needed at that time, it shouldn't have been restricted until it was. It's in fact only since the media and local politicians have started flagging the continued delays in getting it done that a flurry of work has started on these sections in the last 2 months. But there's plenty of blame to go around - the authorities for not treating this as the critical piece of road infrastructure it is and agreeing a timetable to suit, and the crews involved for cutting off huge chunks of it for no reason. The usual "ah shure it'll be grand!" approach so common in this country. I don't need to be an engineer to see that, nor do I have any sympathy for anyone other than the tens of thousands of commuters caught up in this mess every day as a result.
gilly1910 wrote: » At the end of the day, they are adding a third lane to an existing motorway, hardly a major construction feat in this day and age, and the fact of the matter is that if this was happening in any other country of note, it would be done in half the time. The Irish have been building roads and involved in many other major construction projects in the UK and America for decades all of which get build in half the time. However for some bizarre reason when building in their own country, jobs take twice as long and invariably cost twice as much as originally envisaged.
harr wrote: » I see people now giving out about them cutting down the trees along the side of the motorway to make way for the new hard shoulder.... KCC has confirmed planning permission was granted for this , seemingly it goes against the wildlife act of not cutting hedges between March and August.
lawred2 wrote: » Have you instances to hand of similar projects being done in half the time?
Chris_5339762 wrote: » There is, as far as I am aware, provision in the wildlife act for major infrastructure.
Emme wrote: » Here we go again. Have you instances to hand of similar projects being done outside Ireland in the same amount of time? To be honest I can't imagine Italians sticking to the 60km speed limit as well as the Irish (apart from a little speeding, most of what I have seen is from trucks). Also ze Germans would get very annoyed with the slow and inefficient pace of the roadworks. So who else would put up with this on a main commuter route, apart from the Irish? Maybe the Brits, but they have had a better public transport system than us for years.