JohnC. wrote: » Do the cables go from deck to deck through the pillar, or deck to pillar with an end anchored in the pillar? I'm guessing the former, but I don't know.
m17 wrote: » Bridge deck drawing
m17 wrote: » The barrow crossing 06/04/19 (pic insta_matic instragram) 28/04/19
josip wrote: » It looks like the one on the 28th was taken from higher up, making the gap look much a tad narrower than 3 weeks earlier?
tonc76 wrote: » Unusual to see a drawing in cm? M or mm are generally used, no?
sdanseo wrote: » Each side of the bridge only 4.25m wide or am I reading that diagram wrong?- Surely not one lane each way?
Azatadine wrote: » November? Great! I've been going between Wexford and Waterford through that hell hole New Ross for nearly 20 years so cant wait.
alta stare wrote: » I drive it a few times a week and sometimes i find it the longest hour of my life. I reckon the new bridge will take 20 mins off the journey. The amount of slow moving vehicle's drives me mad.
thomasm wrote: » Two people in the last few days have said to me there is an issue with both ends aligning and that some Spanish contractors who were on site have been sent home while this is looked at. No idea if true or not and could be idle talk.
Azatadine wrote: » Yeah. It will definitely have a significant impact on travel time.....and stress. Nothing worse than sitting in those damn queues. It'll probably have a knock on effect to the Barntown roundabout In Wexford though and that's atrocious in the evenings as it is.
alta stare wrote: » <snip> Backseat modding is not acceptable.
gman2k wrote: » Just to let folks know that the current Google satellite imagery is very recent. Possibly 6 weeks or so. I know a field in it that's close to my house that was only recently ploughed for the first time in decades. Sat images are very clear!
skodacb wrote: » https://imgur.com/a/buiTXHA As of today at the pink rock site. Looks like they're working through the bank holiday weekend.