I think it's about time this issue had its own dedicated thread where updates can be provided on the situation with MSAs (Motorway Service Areas)...
As of this month, we have 435 km of motorway. By this time in 2010, that will have increased to over 800 km (nearly triple what it was two years ago).
The NRA have plans to create 12 service areas (you can view their map in the attachment):
1) M1 - South of Balbriggan
2) M1 - South of Dundalk
3) M4 - West of Enfield
4) M6 - Near Athlone
5) M6 - Rathmorrisey Interchange
6) M7 - Near Mountrath
7) M7 - East of Nenagh
8) M8 - North of Cashel
9) M8 - Near Kilworth
10) M9 - Near Kilcullen
11) M9 - Near Bagenalstown
12) M11 - Between Arklow and Gorey
They are planning an additional one for the M3. When the M18 and M20 are (eventually) finished it is reasonable to expect one MSA on each of them.
CURRENT STAGE:
EIS Plans have been drawn up for:
1) M1 Southern MSA
2) M1 Northern MSA
3) M4 MSA
4) M6 Athlone MSA
5) M9 Kilcullen MSA (Just released)
6) M11 Gorey MSA
The EIS plans for the other 6 areas I have been told will be published over the coming 2-3 months.
The following are at tender stage:
1) M1 Southern MSA
2) M1 Northern MSA
3) M4 MSA
According to the NRA/EIS plans:
> Each service area takes
12 - 18 months to construct...
> The service areas are expected to be operational by
the end of 2010...
> The facilities in each service area will be (but are not limited to):
- Parking (seperate parking for HGVs)
- Fuel Facilities
- Convenience Shop
- Picnic Areas
- Toilets
- Restraunt(s)
- Seating Areas
- Showers
- Information Kiosk
- Children's Play Area
- Telephone Facilities
Please post any updates on the MSAs in this thread...