NRA have this morning advertised for engineering consultancy to design medium to long term solution to the junction!
:):)
L1011 wrote: » There isn't the room for what you're proposing.
spacetweek wrote: » They are providing the M8S - M25E movement. I think you mean M8S-N8W, which is not being provided and should not be.
Kermit.de.frog wrote: » spacetweek wrote: » They are providing the M8S - M25E movement. I think you mean M8S-N8W, which is not being provided and should not be. Yes it should. I think you mean N25W.
Pablo Escobar wrote: » There is no N25W from the Dunkettle as far as I'm aware.
hans aus dtschl wrote: » I think their reason to omit it was because of cost, due to space constraints. I think it's a fairly poor omission, personally. A lot of traffic already rat runs through Rathcooney and Upper Glanmire to get to the Northside business parks and I expect that similar rat running will happen through Glanmire following the interchange upgrade. People will say that there isn't much traffic making this movement, but I can tell you anecdotally that a lot of HGV's, buses and people visiting the city from neighbouring counties make this movement. And the new design sees all of this use the same junction as Little Island traffic. It's destined to fail. The only readily-available fix is to change the signage to send all Dublin-Cork traffic around the N40 southbound and we already that will be over capacity at Douglas, so that won't work either. IMO just another example of critical national infrastructure in Cork being half-done, following in a long tradition after Kinsale Road, Bandon Road, Sarsfield's road interchanges.
marno21 wrote: » 2. This is the most important one. Of the 4 approaches to the interchange, 3 are long distance dual carraigeways to Midleton, Dublin and Ballincollig. The N8 approach slams into a roundabout less than 1km from the interchange. There is no real need to have it freeflow if traffic has to stop there and congestion on the N8 approach into the city will worsen with freeflow from the N40 and the N25, in addition to less impeded flow from the M8.
marno21 wrote: » 1. This isn't like the Rathmorrissey interchange where there is large amounts of vacant flat land around the interchange.
Kermit.de.frog wrote: » Don't think you should use that as an example! Look at the mess they made of that. A "stackabout" instead of a proper freeflow interchange. It would have been cheaper to build it right. :rolleyes: If these decisions are not criticised and challenged the same mistakes will keep being made. There is clearly room for a flyover to cater for the movement in question.
marno21 wrote: » What I was saying is that it's valid to complain about Rathmorrissey not being freeflow because the land is easily there for any type of interchange. The question for the M8->N8 link isn't is the land there, it's how much would it add to the cost and what knock on effects would it have on the rest of the interchange design. The people who designed it obviously decided that the current interchange design was the best to go forward with.
pigtown wrote: » Am I right in thinking that you have to go through those roundabouts to go m40-m8?
Kermit.de.frog wrote: » A bit crude but 3 potential options
AugustusMinimus wrote: » Here’s a question. What will happen to the old Little Island west junction. Looks like the entrance will remain open but the exit removed?
Kermit.de.frog wrote: » What other country in Europe would we be talking about putting a movement like that through two roundabouts on the main route between the two biggest cities? Can you think of one? Well, it's not going to change now so no point arguing the toss. Just don't be surprised when you see the hash they make of the CNR and M20 junctions.
JupiterKid wrote: » Come back on this thread, nay - this forum when you have finished school Kermit...
Kermit.de.frog wrote: » JupiterKid wrote: » Come back on this thread, nay - this forum when you have finished school Kermit... Answer the question. I'm looking for ONE other country and we'll do our research to see if they are as incompetent as we are. P.S No personal insults says one of the mods.
Kermit.de.frog wrote: » Answer the question. I'm looking for ONE other country and we'll do our research to see if they are as incompetent as we are. P.S No personal insults says one of the mods.
Engineers confirmed today that the Silversprings Interchange scheme on the eastern approach to the city centre will get underway on October 1 and should be complete before the end of the year
Separately, improvement works are also proposed at the Little Island interchange.
Kermit.de.frog wrote: » Small issue but I see on the documentation they are going for those hideous bulky gantries (these must be standard now) they put on the M50 (the old British style) instead of going for the slender, more visually appealing modern ones you see around US, Europe and UK. Sums up Ireland really ala the stackabout at Rathmorrisey. Ape what the Brits were doing 20 years ago 20 years later and remain behind the times.
Kermit.de.frog wrote: » Sums up Ireland really