s14driftking wrote: » the bridges. Tarring is starting next week on the main line at nites. There is no nonense made up here from me I was inducted into the site in the last while.
Kevwoody wrote: » How are they 9 months behind?? The project manager gave a radio interview saying they'd be finished on time next year.
CeilingFly wrote: » Why do people make up such nonsense?
s14driftking wrote: » Be more in there mind throwing more man power at it there already 9 months behind atm.
s14driftking wrote: Be more in there mind throwing more man power at it there already 9 months behind atm.
sonyvision wrote: » While i do agree with speed enforcement. This will cause nearly everybody jamming in the breakings wouldn't be surprised if this cause rear end accidents. Even if they are doing 60 they will break I bet Why can't they install average speed cameras. If i recall some time a few years back these were along the M7 or M9 running accross yellow poles with signs warning of these... (doubt where switched on)
beertons wrote: » Not build related, but Go Safe vans will be deployed from Monday to slow the traffic down even more.
CeilingFly wrote: » Its less than half the length of 9-10, doesn't require two new junctions and less pipework is involved. (the utility trunk was laid last year) Also the jct 9-10 work has taken 6 months. It started 3rd week jan and there was a week of snow delay. So almost 8 months to do half the distance won't be an issue. But what is it with these negative ninnies? Its like a throwback to the eighties when local councils did the work and unions did everything to delay / extend works because that's what public sector unions do. These days its international conglomerates and they almost always finish ahead of time.
Chris_5339762 wrote: » True yes, but they have nothing done from J10 - J11, at all. I just can't see how they'll do that bit that quickly.
Chris_5339762 wrote: » Eight months to complete an online widening? Thats pie in the sky. Don't get me wrong I'd be delighted if they managed it, but when has an online widening ever been done that quickly anywhere. (We won't count China etc)
Patww79 wrote: » Google maps was showing 27 minutes delay on it around midday with no incidents. Used the N81.
regedit wrote: » quite a lot of human and machinery activity now between Naas and Newbridge but not sure what the builders have done as the traffic has become much heavier. Yesterday (Friday), as early as 13:30, the traffic was at a standstill from before Kill and then very heavy all the was to the Newbridge exit! Schools out and people on holidays! It may get much worse come September... Shame SIAC/Colas wont come here or on twitter to update people on the progress and next steps
Cookiemunster wrote: » Well done picking the one of the most complicated infrastructure projects ever undertaken in the history of the state, which opened 12 years ago, as an example. Almost every road infrastructure project in Ireland over that last 15 years has been on time (with many well ahead of time) and on budget.
benny79 wrote: » Was there not false promises giving about the port tunnel?? just saying.. Over time and over budget.. To be honest I don't really care I just hope its finished as soon as possible as commuting is a nightmare! I driving 20 years and never had a crash until this year! My fault though. I went the back roads because of a crash and knew the traffic be mental and was half asleep.. You really have to be on the ball driving them back roads..
CeilingFly wrote: » I was saying its just a couple of layers of tarmac for the current section to be finished - yes there's a little more to it, but in comparison to the work that has been completed its now down to the dressing part and that's relatively easy. And if the project manager say just two days ago that it is on schedule for March 2019 completion of the mainline works, then certain posters have to accept that. These are major international contractors. they don't give false promises just to appease people, they give real information.
Tyson Fury wrote: » Nice to hear the 3 lanes will be open in March, they're badly needed. Was like the wild West yesterday evening, cars cutting into lanes, lads jamming on the brakes other cars tearing down the hard shoulder. I saw a car flying down the hard shoulder, a squad car pulled out to take chase but unfortunately he didn't indicate or look and ploughed straight into the car that was coming behind.
marno21 wrote: » 60km/h speed limit to be extended to J11 M9 from 6am Saturday as per AA Roadwatch
rameire wrote: » unfortunately its not just a couple of layers of tarmac as you question. the next stages once all cabline and pipework is complete will be laying hardcore to raise the level of the base to then be able to lay 3 to 4 layers of tarmac. .