CeilingFly wrote: » Yep, the project manager was on rte radio. Completion of three lanes both ways end March 2019 Move to new part of road in stages. October 2018 and Dec 2018 - this to allow current lanes to be resurfaced. So seems a lot better than envisaged. He also said there have been no delays.
NedNew2 wrote: » The contractor is aiming to have the mainline works completed by March 2019.http://www.m7upgrade.com/ Very heavy traffic and delays over the weekend due to the extended 60 km/h zone.
marno21 wrote: » When was the project manager on the radio?
roadmaster wrote: » It just depends on what you describe as being finished. You could have all lanes open but work for months afterwords taking place on verges and sideroads
benny79 wrote: » That be fine by me! but he said the 3 lanes be finished by March next year. Considering they haven't finished them from J9 to J10 and are only starting J10 to J11 I cant see it been finished by then. But I really hope Im wrong! To me the widening of the 3 lanes are a priority!
marno21 wrote: And the work will still be continuing in the two junctions and the Sallins bypass
Redsoxfan wrote: » Oh... I thought it was all one project? Is the 3 lane upgrade separate to the bypass and new junctions? I took him to mean that everything would be open.
CeilingFly wrote: » So the project manager give a verbal update on public radio giving full details and timeline and you don't believe it???? Why would a very experienced project manager go on national radio and tell a lie? The works from jct 10 - 9 are almost finished. Putting a couple of top layers of tarmac is the quickest part of the work. That was a 9km section. Work started in late Jan / early February. Its near finished now, 6 months later. The remaining section is half that size and work starts in 2 weeks. Even the lay person can easily see that the road will open by next March (8 months away) looking at current progress. But some people will always search for a negative in everything. :mad:
benny79 wrote: » Do Politicians not go on radio & TV and lie all the time?? The so called leaders of our Country! So your trying to tell me a project manager cant get it wrong? Just a couple of layers of tarmac you say? Well I suggest you take a look the next time your passing as I drive that road twice a day and have done so the last 15 years and its far from a couple of layers of tarmac. There is still pipe to be laid unless these are leftover, there's still big pits or holes, steel is still sticking up, which I say is for support for something so concrete will have to be poured over them and there's roughly a 2 ft drop from the level of the road for most the stretch of the works. Now maybe you have more experience than me, which is fair enough. Hence why I said I hope I'm wrong... As I'm just giving my opinion as a lay man
rameire wrote: » unfortunately its not just a couple of layers of tarmac as you question. the next stages once all cabline and pipework is complete will be laying hardcore to raise the level of the base to then be able to lay 3 to 4 layers of tarmac. Then the next stage will be to move a lane of traffic onto the new layer. or possibly what they may do is move the two eastbound lanes onto the new two lanes created then scrape away the hard shoulder and the lane 1 from the eastbound carriageway. relay the tarmac 3 or four layers to being it up to the new layer of the new lanes. then move the eastbound back onto the new hard shoulder and lane1. then move the westbound hard shoulder and lane 1 onto the new two middle lanes, scrape the tarmac for the old lanes, lay new tarmac to the new level. then, move the lanes back to the hardshoulder and lane 1. Once all the above is done then they will lay the central median barrier. line the road. then open the new lanes. bish bash bosh.
rameire wrote: » unfortunately its not just a couple of layers of tarmac as you question. the next stages once all cabline and pipework is complete will be laying hardcore to raise the level of the base to then be able to lay 3 to 4 layers of tarmac. .
marno21 wrote: » 60km/h speed limit to be extended to J11 M9 from 6am Saturday as per AA Roadwatch
Tyson Fury wrote: » Nice to hear the 3 lanes will be open in March, they're badly needed. Was like the wild West yesterday evening, cars cutting into lanes, lads jamming on the brakes other cars tearing down the hard shoulder. I saw a car flying down the hard shoulder, a squad car pulled out to take chase but unfortunately he didn't indicate or look and ploughed straight into the car that was coming behind.
CeilingFly wrote: » I was saying its just a couple of layers of tarmac for the current section to be finished - yes there's a little more to it, but in comparison to the work that has been completed its now down to the dressing part and that's relatively easy. And if the project manager say just two days ago that it is on schedule for March 2019 completion of the mainline works, then certain posters have to accept that. These are major international contractors. they don't give false promises just to appease people, they give real information.
benny79 wrote: » Was there not false promises giving about the port tunnel?? just saying.. Over time and over budget.. To be honest I don't really care I just hope its finished as soon as possible as commuting is a nightmare! I driving 20 years and never had a crash until this year! My fault though. I went the back roads because of a crash and knew the traffic be mental and was half asleep.. You really have to be on the ball driving them back roads..
Cookiemunster wrote: » Well done picking the one of the most complicated infrastructure projects ever undertaken in the history of the state, which opened 12 years ago, as an example. Almost every road infrastructure project in Ireland over that last 15 years has been on time (with many well ahead of time) and on budget.
regedit wrote: » quite a lot of human and machinery activity now between Naas and Newbridge but not sure what the builders have done as the traffic has become much heavier. Yesterday (Friday), as early as 13:30, the traffic was at a standstill from before Kill and then very heavy all the was to the Newbridge exit! Schools out and people on holidays! It may get much worse come September... Shame SIAC/Colas wont come here or on twitter to update people on the progress and next steps
Patww79 wrote: » Google maps was showing 27 minutes delay on it around midday with no incidents. Used the N81.