MBSnr wrote: » Is this for certain? Each house has a dedicated port, so there is no issue of getting in first? I'm stuck in an 18 month Vodafone contact... Don't fancy buying it out (if I don't need to) if FTTH magically becomes available for me in mid 2017
mdfire wrote: » Its even more frustrating in that a fibre cabinet was installed two weeks ago less than 1km from the house. Its still showing as planned and i cant get any date from eir. At least if I had that up and running it would be an improvement on the 2mb im getting at min.
mdfire wrote: » Officially its assigned by Eircode. Ive been told that if its not taken up then it could, theoretically, be reassigned.
The Cush wrote: » I posted about this cabinet the day work commenced, completed many months ago but hasn't gone live yet, still showing as completion work in progress.
pegasus1 wrote: » I would say that it wont and can/t due to the NBP... Maybe if a new build were to happen in an area where fibre has been fully run and installed then yes, But I presume there is some extra ports in each splice unit to allow for this..
mdfire wrote: » The fibre stopped 250m short of me on our lane. We have the crazy situation of there being 2 fibre boxes each of which has four ports. The eir rep told me that only one of the 6 properties served by it wanted fibre broadband. So there is 7 spare ports just down the lane and i cant get it. Is there another country in the western world where this would be allowed to happen?
SteveD92 wrote: » Our installation for FTTH was scheduled for today. Engineer was on site and once he went to connect it he realised the code on the box which was running the fibre from the road to the house was different to what he had been issued and couldn't complete the install. Called Eir and they said it was an isolated issue and the guy on the phone hadn't heard of it happening before and had to leave it with him to sort out before getting another installation date. Said it would have to be manually fixed (whatever that means?) Any idea as to what the code has to do with it?
Deleted User wrote: » I suspect that if you offered to pay for the extra work involved in stringing up the fibre, they'd do it. After all it's a simple task of a few pole clips and a couple of hundred metres of fibre instead of 50 metres or so for a standard rural installation. My house is located half way between two splice boxes and I expect they'll need about 100m of fibre to get from the splice to the NTU in the house. A duct and three poles to the splice.
mdfire wrote: » So explain to me why it stopped 250m in the other direction also? The road is a loop of the main road and they came in both sides and left out about 500m in the middle where most of the houses are. Other parts of the area which are more remote (by several km) are served.
pegasus1 wrote: » Has the new motorway build been progressed to an extent that ducting is laid on a flyover or underpass?.. Perhaps when it is they will come out to do your section...
irishchris wrote: » They have ducting laid under the motorway for provison of water on our old access road. They then laid new ducting and copper wire on the new access road to our houses even though few weeks later they were fitting fibre to the adjoining roads and completely ignored these houses. Would have made more sense to have laid a fibre line when they digging the new access road for ducting and laying new copper cable anyway but unfortunately not :-(
Gonzo wrote: » The map is updated, Dunshaughlin has a live date of 8th March!!!!!
plodder wrote: » It's possibly totally different arms of Openeir doing the copper wire ducting as compared with the fibre. I'd be surprised if they didn't leave space for fibre as well.
plodder wrote: » We're moved from early/mid 2017 to Spring/Summer 2017. Not sure what that's supposed to mean. I guess Summer could mean August, which is a slip. Interesting that the cabinet status in the next village went from "planned" to "live". No build stage .
MajesticDonkey wrote: » Mine went from Winter 2017/Spring 2018 to Winter 2018