Advertisement
If you have a new account but are having problems posting or verifying your account, please email us on hello@boards.ie for help. Thanks :)
Hello all! Please ensure that you are posting a new thread or question in the appropriate forum. The Feedback forum is overwhelmed with questions that are having to be moved elsewhere. If you need help to verify your account contact hello@boards.ie
Hi all! We have been experiencing an issue on site where threads have been missing the latest postings. The platform host Vanilla are working on this issue. A workaround that has been used by some is to navigate back from 1 to 10+ pages to re-sync the thread and this will then show the latest posts. Thanks, Mike.
Hi there,
There is an issue with role permissions that is being worked on at the moment.
If you are having trouble with access or permissions on regional forums please post here to get access: https://www.boards.ie/discussion/2058365403/you-do-not-have-permission-for-that#latest

Change insulation from our original plan

  • 18-09-2014 7:15pm
    #1
    Registered Users, Registered Users 2 Posts: 226 ✭✭


    Hi all! Quick question!

    We have our planning but haven't put in our commencement notice yet. In our planning we have a 120mm cavity with 100mm insulation and a 50mm insulated slab on the inside. Would it be much hassle to change it so all the insulation is in the cavity and have the inner block as a sort of thermal conductor.

    And I we do go for this would 150mm insulation still suffice or would we need more?


Comments

  • Moderators, Home & Garden Moderators Posts: 10,141 Mod ✭✭✭✭BryanF


    Your design & construction certifier need to review and agree and revise the building control submitted drawings. Your builder needs to price the difference with the revised architects wall/window/eaves/floor junction/door threshold details to hand.