Public Consultation on a Micro-generation Support Scheme (MSS) in Ireland

1356710

Comments

  • Registered Users Posts: 3,954 ✭✭✭mp3guy


    KCross wrote: »
    I'm worried about this element of the scheme as they might come up with some mad system administered by SEAI which will just make the whole thing more cumbersome than it should be.

    Sounds about right.


  • Moderators, Sports Moderators Posts: 18,650 Mod ✭✭✭✭slave1


    Oh absolutely, red stupid tape like having to print off and snailmail photos to the SEAI to adhere to EV Home Chargepoint grant criteria, emails not accepted, the mind boggles


  • Moderators, Home & Garden Moderators Posts: 5,756 Mod ✭✭✭✭graememk


    slave1 wrote: »
    Oh absolutely, red stupid tape like having to print off and snailmail photos to the SEAI to adhere to EV Home Chargepoint grant criteria, emails not accepted, the mind boggles

    They dont even have the decency to snail mail back the confirmation that they have got it, they email it back to you...


  • Registered Users Posts: 1,470 ✭✭✭MAULBROOK


    championc wrote: »
    They already know the size of people's systems, from the NC6 Form, which is tied to your MPRN

    My NC6 stated a 4.8kw system, it now a 6.2kw and thats not on any NC6 form.


  • Registered Users Posts: 545 ✭✭✭idc


    MAULBROOK wrote: »
    My NC6 stated a 4.8kw system, it now a 6.2kw and thats not on any NC6 form.

    I guess thats another question? Are you supposed to send in a new NC6 if you change your system. I did notice on form it has spaces for up to 3 inverters!!


  • Advertisement
  • Registered Users Posts: 10,803 ✭✭✭✭the_amazing_raisin


    KCross wrote: »
    I'd agree. Realistically the export meter (smart or otherwise) is the only measure they can reliably use. Anything inside the premise will be wide open to abuse. Eirgrid wont go there.


    There's only 3 ways I can see it being enforceable

    1. Installations over 6kWp (I think that's the limit???) are required to go to 3 phase to allow more export power. There'll probably be an assessment when applying for export to determine of your grid connection can handle the peak power. Presumably Eirgrid would need to be informed then of any expansions to your PV array
    2. The export meter has a built in limiter to prevent more power from being exported
    3. Eirgrid monitor the output of the smart meter closely, they can update every 30 mins so they could flag any premises that are exporting more than the limit quite quickly

    "The internet never fails to misremember" - Sebastian Ruiz, aka Frost



  • Registered Users Posts: 1,470 ✭✭✭MAULBROOK


    idc wrote: »
    I guess thats another question? Are you supposed to send in a new NC6 if you change your system. I did notice on form it has spaces for up to 3 inverters!!

    Not a clue


  • Registered Users Posts: 3,954 ✭✭✭mp3guy


    There's only 3 ways I can see it being enforceable

    1. Installations over 6kWp (I think that's the limit???) are required to go to 3 phase to allow more export power. There'll probably be an assessment when applying for export to determine of your grid connection can handle the peak power. Presumably Eirgrid would need to be informed then of any expansions to your PV array
    2. The export meter has a built in limiter to prevent more power from being exported
    3. Eirgrid monitor the output of the smart meter closely, they can update every 30 mins so they could flag any premises that are exporting more than the limit quite quickly

    Why would higher than 6kW export require three phase? You can import 15kW on single phase, why not export?

    How would a meter "limit" the power? It has to go somewhere, and I doubt it could just be dissipated. It would require communication with individual inverters to scale down the array.


  • Moderators, Home & Garden Moderators Posts: 5,756 Mod ✭✭✭✭graememk


    Making sure the premium tariff they are suggesting isnt exploited by putting limits on things just complicated things to no end.

    id be happy with the average wholesale rate (even if there is a 3% reduction on it or something)

    Will have to wait until this consultation process is over... Fun.

    I'd say they wont limit the export, just not pay you for it!


  • Registered Users Posts: 545 ✭✭✭idc


    mp3guy wrote: »
    Why would higher than 6kW export require three phase? You can import 15kW on single phase, why not export?.

    Because that's the rules as defined by esb networks. https://www.esbnetworks.ie/new-connections/generator-connections/connect-a-micro-generator
    25 amperes (6kW) at low voltage [230 volt] when the connection is single phase
    16 amperes(11kW) at low voltage [230/400 volt] when the connection is three phase


  • Advertisement
  • Registered Users Posts: 3,954 ✭✭✭mp3guy


    idc wrote: »

    My point is that it was implied you had to go to three phase for some technical reason as opposed to the ESB's arbitrary 6kW rule, which seems like it may change after this consulation is over. You can for example, export more than 6kW if you go the more awkward route that doesn't involve the "express" NC6 form that suits most for microgeneration - https://www.esbnetworks.ie/new-connections/generator-connections/connect-a-renewable-embedded-generator. The ESB has numerous generators connected on the LV network in the tens of kW.


  • Registered Users Posts: 10,803 ✭✭✭✭the_amazing_raisin


    mp3guy wrote: »
    My point is that it was implied you had to go to three phase for some technical reason as opposed to the ESB's arbitrary 6kW rule, which seems like it may change after this consulation is over. You can for example, export more than 6kW if you go the more awkward route that doesn't involve the "express" NC6 form that suits most for microgeneration - https://www.esbnetworks.ie/new-connections/generator-connections/connect-a-renewable-embedded-generator. The ESB has numerous generators connected on the LV network in the tens of kW.


    I agree the 6kW rule doesn't make sense and I'll be saying as much in my response to the consultation. Nevertheless, the ESB make the rules and we have to abide by them :(


    I looked at the details for the higher power generator and you need to provide numerous design documents and certificates, which will probably need an electrical engineer to provide. There's also a non-refundable a connection fee deposit of around €2k if I recall . I doubt you'll make enough on export to pay for the cost of the connection

    "The internet never fails to misremember" - Sebastian Ruiz, aka Frost



  • Registered Users Posts: 3,954 ✭✭✭mp3guy


    I looked at the details for the higher power generator and you need to provide numerous design documents and certificates, which will probably need an electrical engineer to provide. There's also a non-refundable a connection fee deposit of around €2k if I recall . I doubt you'll make enough on export to pay for the cost of the connection

    Yes, the red tape surrounding NC5(A) is something that comes up often. NC6 is much easier for the many PV installations happening these days.

    The fees are listed in that link I posted above, for e.g. it's €773 for > 11kW ≤ 50kW. With a decent sized array, you might make that back from FIT within a year or two. Or, given a big enough array and home usage, will save yourself that money on bills if you were otherwise unable to get such a big installation.


  • Registered Users Posts: 12,068 ✭✭✭✭KCross


    mp3guy wrote: »
    My point is that it was implied you had to go to three phase for some technical reason as opposed to the ESB's arbitrary 6kW rule, which seems like it may change after this consulation is over.

    I dont think its that arbitrary. Going over 6kW means they have to do an assessment to see if there is any infrastructure work required to support it based on other micro-generators on the same line etc.

    e.g. if you opened it up that every house could get 11kW you could on a sunny day overload local infrastructure if several houses were dumping to the grid at the same time... the 6kW "express" option is there for a reason.

    The consultation paper says that "everyone" could install 3kW PV today and the grid would be fine and in lots of cases it could take 6kW without upgrades being required but beyond that they would have to do infrastructure upgrades or at least assess your particular location.

    I dont think they'll change these requirements particularly since the document makes several references to self-consumption being the focus.


  • Registered Users Posts: 3,954 ✭✭✭mp3guy


    KCross wrote: »
    I dont think its that arbitrary. Going over 6kW means they have to do an assessment to see if there is any infrastructure work required to support it based on other micro-generators on the same line etc.

    e.g. if you opened it up that every house could get 11kW you could on a sunny day overload local infrastructure if several houses were dumping to the grid at the same time... the 6kW "express" option is there for a reason.

    The consultation paper says that "everyone" could install 3kW PV today and the grid would be fine and in lots of cases it could take 6kW without upgrades being required but beyond that they would have to do infrastructure upgrades or at least assess your particular location.

    I dont think they'll change these requirements particularly since the document makes several references to self-consumption being the focus.

    Right, yes. The impression I have is that it's first come first served when it comes to that capacity, which you can view here https://www.esbnetworks.ie/new-connections/generator-connections/network-capacity-map.

    So, if you want to be able to do something unusual and export more than standard amounts, better nab any available capacity before your neighbours get PV.


  • Registered Users Posts: 10,803 ✭✭✭✭the_amazing_raisin


    KCross wrote: »
    I dont think its that arbitrary. Going over 6kW means they have to do an assessment to see if there is any infrastructure work required to support it based on other micro-generators on the same line etc.

    e.g. if you opened it up that every house could get 11kW you could on a sunny day overload local infrastructure if several houses were dumping to the grid at the same time... the 6kW "express" option is there for a reason.

    The consultation paper says that "everyone" could install 3kW PV today and the grid would be fine and in lots of cases it could take 6kW without upgrades being required but beyond that they would have to do infrastructure upgrades or at least assess your particular location.

    I dont think they'll change these requirements particularly since the document makes several references to self-consumption being the focus.


    It's showing a pretty severe lack of ambition though, indicates the ESB is unwilling to do any work to make the grid able to handle more microgeneration

    "The internet never fails to misremember" - Sebastian Ruiz, aka Frost



  • Registered Users Posts: 3,954 ✭✭✭mp3guy


    It's showing a pretty severe lack of ambition though, indicates the ESB is unwilling to do any work to make the grid able to handle more microgeneration

    They'll continue fighting tooth and nail to prevent progress.


  • Registered Users Posts: 12,068 ✭✭✭✭KCross


    mp3guy wrote: »
    Right, yes. The impression I have is that it's first come first served when it comes to that capacity, which you can view here https://www.esbnetworks.ie/new-connections/generator-connections/network-capacity-map.

    So, if you want to be able to do something unusual and export more than standard amounts, better nab any available capacity before your neighbours get PV.

    The consultation clearly says that everyone should have access to the scheme so I doubt they will refuse your application because your neighbors have availed of it already. If there are upgrades required the consumer wont have to directly pay for those upgrades but if you ask for a larger array than they decide you will probably have to pay a shortfall.

    It would work the same as your incoming grid connection. We are all entitled to a grid connection and the regulator sets the price for a connection upto 16kVA... if you want more than that you pay extra for the privilege. They will likely do the same here for any upgrades related to export.
    It's showing a pretty severe lack of ambition though, indicates the ESB is unwilling to do any work to make the grid able to handle more microgeneration

    The document says that they have done a study and everyone could install 3kWp today and the grid would be fine as is so I dont see an issue unless your plan is to install a large array (>10kWp).

    For sure they are not in favour of promoting micro-generation in general but the 6kW limit isnt really a manifestation of that. If you want a larger array you can have it and you pay for the infrastructure upgrades accordingly.... in the very same way you can have a 20-30kVA grid connection into your house as well if you like but you pay the fees accordingly.


    I think we need to understand also that the proposed FiT is not free to the taxpayer. It is a subsidy that other taxpayers will have to pay for. So, opening it up to allow unfettered access and have people putting in huge arrays just to make money off other taxpayers isnt reasonable.... we dont need another "ash for cash" scheme like they have in the North.

    Its easy to say, i'm generating electricity and giving it to Eirgrid for free.... but its not as simple as that. The big generators still have to be on standby and paid for when the clouds roll over and you stop exporting.... hence why its a subsidy that is being socialised.


  • Registered Users Posts: 64,702 ✭✭✭✭unkel


    KCross wrote: »
    if you opened it up that every house could get 11kW you could on a sunny day overload local infrastructure
    KCross wrote: »
    The consultation paper says that "everyone" could install 3kW PV today and the grid would be fine.

    Do you not think those statements contradict each other?

    So if every household could export 3kW that means that on the day the FIT comes in, the grid would be fine if a quarter of all households overnight have a 11kwp install. Which of course is not going to happen, the uptake of micro generation will be very, very gradual (would take years for even that level of 3kW per household - we might never get that far) and the ESB will monitor this and over time they can adjust the grid to allow for a lot more micro generation than we have today.

    Other countries in the EU are years ahead of us and they didn't seem to have massive problems...


  • Registered Users Posts: 10,803 ✭✭✭✭the_amazing_raisin


    unkel wrote: »
    Do you not think those statements contradict each other?

    So if every household could export 3kW that means that on the day the FIT comes in, the grid would be fine if a quarter of all households overnight have a 11kwp install. Which of course is not going to happen, the uptake of micro generation will be very, very gradual (would take years for even that level of 3kW per household - we might never get that far) and the ESB will monitor this and over time they can adjust the grid to allow for a lot more micro generation than we have today.

    Other countries in the EU are years ahead of us and they didn't seem to have massive problems...

    I think they did mention they can support larger export with a smaller uptake, which is the more likely scenario

    "The internet never fails to misremember" - Sebastian Ruiz, aka Frost



  • Advertisement
  • Registered Users Posts: 12,068 ✭✭✭✭KCross


    unkel wrote: »
    Do you not think those statements contradict each other?

    So if every household could export 3kW that means that on the day the FIT comes in, the grid would be fine if a quarter of all households overnight have a 11kwp install. Which of course is not going to happen, the uptake of micro generation will be very, very gradual (would take years for even that level of 3kW per household - we might never get that far) and the ESB will monitor this and over time they can adjust the grid to allow for a lot more micro generation than we have today.

    Other countries in the EU are years ahead of us and they didn't seem to have massive problems...

    I don’t follow your logic at all. I don’t see a contradiction.

    They simply want to ensure that you don’t have one person taking all the capacity on a transformer to the detriment of everyone else having access.

    It’s also about spreading the subsidy to as many houses as possible.

    Which is better... 3 houses with 10kWp arrays or 10 houses with 3kWp arrays!


  • Registered Users Posts: 64,702 ✭✭✭✭unkel


    KCross wrote: »
    Which is better... 3 houses with 10kWp arrays or 10 houses with 3kWp arrays!

    10 houses with 10kwp arrays :p

    My point is if they are saying that if every house in the land would export 3kW, that's fine. So what's the problem here? It would take many years before we reach that level even if anyone so inclined would start installing 10kwp arrays from tomorrow


  • Registered Users Posts: 12,068 ✭✭✭✭KCross


    unkel wrote: »
    10 houses with 10kwp arrays :p

    My point is if they are saying that if every house in the land would export 3kW, that's fine. So what's the problem here? It would take many years before we reach that level even if anyone so inclined would start installing 10kwp arrays from tomorrow

    There isnt a problem per se.
    The discussion had two tangents...

    - Why the current 6kW export limit dictated by Eirgrid under the NC6 system
    - Why the 30% export limit proposed by this consultation.

    Im just explaining the logic for those two things as laid out in the consultation paper.

    Its not all about "can the grid take it". The taxpayer is funding this and so part of it is about value for money.


  • Registered Users Posts: 3,954 ✭✭✭mp3guy


    I think this consultation has just added more confusion to the mix.

    So today, the grid could take, on average, 3kWp export from every house. So, what does that mean? What does it mean for existing 6kW installs, future installs > 3kW. Waiting lists? Payment for infrastructure upgrades if your neighbour got in there first? A cap on all installs to 3kWp unless you pay even if there is capacity?


  • Registered Users Posts: 64,702 ✭✭✭✭unkel


    KCross wrote: »
    The taxpayer is funding this and so part of it is about value for money.

    I haven't thought this through, but what makes you think the taxpayer is paying for this? Is it not just basically your utility provider that buys from you at the same rate as they buy from their wholesale suppliers? So they pay you 5c and sell it onto your neighbour for 15c :p


  • Registered Users Posts: 12,068 ✭✭✭✭KCross


    mp3guy wrote: »
    I think this consultation has just added more confusion to the mix.

    It has certainly raised additional questions because they havent clearly laid out how it will be implemented but I suppose thats the whole point of a consultation... to get feedback.
    mp3guy wrote: »
    So today, the grid could take, on average, 3kWp export from every house. So, what does that mean?

    It means that no grid upgrades would be required to support anyone installing 3kWp of Solar on their roof.
    mp3guy wrote: »
    What does it mean for existing 6kW installs, future installs > 3kW.

    Existing installs will continue as is.... likewise for future installs but they are suggesting that the FiT be capped somehow. I still cant see how they will do that.

    mp3guy wrote: »
    Payment for infrastructure upgrades if your neighbour got in there first? A cap on all installs to 3kWp unless you pay even if there is capacity?

    That would be for the CRU to decide but I doubt they'd do that as long as you stay within the 6kWp thats there already today.


    unkel wrote: »
    I haven't thought this through, but what makes you think the taxpayer is paying for this? Is it not just basically your utility provider that buys from you at the same rate as they buy from their wholesale suppliers? So they pay you 5c and sell it onto your neighbour for 15c :p

    Not exactly, the taxpayer (via a proposed increased PSO levy) is on the hook for 10s of millions.

    Its all in the docs but basically there are two proposed payments....

    CEG... a minimum fixed guaranteed payment per kWh provided to you for your excess, based off the average annual Day-ahead market price. I dont remember there being a cost to the tax payer for this payment. It is from your provider as you have detailed above. The provider is expected to manage this payment themselves ensuring they dont lose their shirt on it by adjusting their retail rates as they see fit to protect themselves from market price fluctuations.

    CEP... a premium payment on top of the CEG which is proposed to be funded by a PSO levy increase which is being paid to close what they call the "viability gap" (the difference between paying for the system to the value you get out of it). The payment is for 15 years and phased out then as its expected that install costs will drop to make up the shortfall. Your provider will give you this CEP payment also but they claim it back off the regulator via the PSO levy.


  • Registered Users Posts: 64,702 ✭✭✭✭unkel


    KCross wrote: »
    CEP... a premium payment on top of the CEG which is proposed to be funded by a PSO levy increase which is being paid to close what they call the "viability gap" (the difference between paying for the system to the value you get out of it). The payment is for 15 years

    WTF? What imbecile / communist came up of that stupid idea? Just pay the wholesale rate of the moment. Not guaranteed. Whatever it is. Be it 1c, 5c or 20c. Or even nothing in 10 years time from now and hopefully every single roof in Ireland is plastered with PV

    Zero cost to the tax payer. And a lot less work to do for the government to bring our emissions down and reduce our fines. Or in other words a saving to the tax payer


  • Registered Users Posts: 12,068 ✭✭✭✭KCross


    unkel wrote: »
    WTF? What imbecile / communist came up of that stupid idea? Just pay the wholesale rate of the moment. Not guaranteed. Whatever it is. Be it 1c, 5c or 20c. Or even nothing in 10 years time from now and hopefully every single roof in Ireland is plastered with PV

    Zero cost to the tax payer. And a lot less work to do for the government to bring our emissions down and reduce our fines. Or in other words a saving to the tax payer

    The assessment is that you wouldn’t have an ROI then which means you won’t have the wide scale uptake we need and hence we miss our target and presumably fines ensue.

    Bear in mind that this proposal could be replacing the grant.


  • Registered Users Posts: 12,173 ✭✭✭✭Calahonda52


    KCross wrote: »
    The assessment is that you wouldn’t have an ROI then which means you won’t have the wide scale uptake we need and hence we miss our target and presumably fines ensue.

    Bear in mind that this proposal could be replacing the grant.

    This will only feed back into the price of panels going up, so no benefit to Joe and Mary Domestic.
    This proposed system, like all the grant schemes here are fundamentally skewed to benefit the supplier of the hardware.
    Just look at how profitable Ki**span got from insulation and solar thermal grants through lobbying of, initially FF Government, making millionaires of a few of the elite.

    “I can’t pay my staff or mortgage with instagram likes”.



  • Advertisement
  • Registered Users Posts: 12,068 ✭✭✭✭KCross


    This will only feed back into the price of panels going up, so no benefit to Joe and Mary Domestic.
    This proposed system, like all the grant schemes here are fundamentally skewed to benefit the supplier of the hardware.

    It’s not a grant scheme though. We already have a grant scheme with inflated prices as you suggest. Hopefully they ditch that.