Reed bed instead of raised percolation area

Options
  • 17-07-2019 10:22pm
    #1
    Registered Users Posts: 1,061 ✭✭✭


    Would it be an option to install a 'Reed bed' ICW instead of a normal raised percolation area in a garden of a one off rural house? House is built and just about to begin on this step but would much prefer a reed bed. Are there planning issues or would they be happy to allow this change? This would be installed after the septic tank (biocycle unit)

    Thanks


Comments

  • Moderators, Home & Garden Moderators Posts: 10,140 Mod ✭✭✭✭BryanF


    Whatever is submitted as part of Planning, you build.


  • Registered Users Posts: 1,061 ✭✭✭gutteruu


    The site plan showed a percolation area, but application and planners report roughly state "waste water treatment to be built in accordance with EPA's guidance on wastewater treatment for single house". That document is quite happy with reed bed systems and outlines minimum specs. Would it be an all out refusal from planners, or is there any wiggle room?


  • Registered Users Posts: 895 ✭✭✭brav


    gutteruu wrote: »
    The site plan showed a percolation area, but application and planners report roughly state "waste water treatment to be built in accordance with EPA's guidance on wastewater treatment for single house". That document is quite happy with reed bed systems and outlines minimum specs. Would it be an all out refusal from planners, or is there any wiggle room?

    Usually the full planning would be more specific than that, and the report from the engineer on the percolation test would have what they recommended with planning agreeing to this.

    The drawing itself might only show percolation area, but one of the donunents attached should show what you planned on putting in


  • Registered Users Posts: 1,061 ✭✭✭gutteruu


    The plans submitted do show a sectional drawing with a raised percolation area and stipulate a "P6 Envirocare unit and raised percolation area". The percolation test went in as normal.

    The planners report states "The treatment plant and percolation system shall be designed, installed and operated in accordance with the EPA publication "EPA wastewater treatment manuals - treatment Systems forsingle houses or otherwise in accordance with alternative proposals submitted by the applicant and approved by Galway County Council"

    The envirocare unit has gone in. It was just to change the percolation are to a series of ICW reed bed


  • Subscribers Posts: 40,989 ✭✭✭✭sydthebeat


    A percolation area is a secondary means of treatment.
    A reed bed is a tertiary means of treatment.

    They are not interchangeable.