Advertisement
If you have a new account but are having problems posting or verifying your account, please email us on hello@boards.ie for help. Thanks :)
Hello all! Please ensure that you are posting a new thread or question in the appropriate forum. The Feedback forum is overwhelmed with questions that are having to be moved elsewhere. If you need help to verify your account contact hello@boards.ie
Hi there,
There is an issue with role permissions that is being worked on at the moment.
If you are having trouble with access or permissions on regional forums please post here to get access: https://www.boards.ie/discussion/2058365403/you-do-not-have-permission-for-that#latest

Silage wall concrete

  • 03-04-2023 8:41pm
    #1
    Registered Users, Registered Users 2 Posts: 1,096 ✭✭✭


    What is the time required to cure the concrete of a 2.5m-3m silage wall? As in when is it considered fit for purpose. Hoping to fit pit in it this year if I can. TIA



Comments

  • Registered Users, Registered Users 2 Posts: 2,377 ✭✭✭DBK1


    Grant spec requires 28 days. I’d be trying to give it at least that if at all possible, especially for walls.

    Concrete should be kept wet for the first week or so after pouring for proper curing. If you can wet it with a hose 2 or 3 times a day for the first week it’s the proper way to cure it.