Advertisement
If you have a new account but are having problems posting or verifying your account, please email us on hello@boards.ie for help. Thanks :)
Hello all! Please ensure that you are posting a new thread or question in the appropriate forum. The Feedback forum is overwhelmed with questions that are having to be moved elsewhere. If you need help to verify your account contact hello@boards.ie
Hi there,
There is an issue with role permissions that is being worked on at the moment.
If you are having trouble with access or permissions on regional forums please post here to get access: https://www.boards.ie/discussion/2058365403/you-do-not-have-permission-for-that#latest

New IrelandOffline blog post

  • 16-05-2010 10:04pm
    #1
    Registered Users, Registered Users 2 Posts: 101 ✭✭


    http://irelandoffline.org/2010/05/the-national-broadband-scheme-again/

    The National Broadband Scheme. A Ghost Broadband System for our Ghost Estates.
    3 Ireland have silently announced that they are unilaterally changing the terms of
    the NBS contract. They will be dropping the data allowance for customers from
    15GB a month of data down to 10GB of data.
    This clearly demonstrates that the 3 Ireland network is not capable of handling
    the data throughput required for the NBS and highlights in general the unsuitability
    of any 3G network to handle the large volumes of data required for such a
    network to be considered as real broadband.
    In our opinion this is clearly a breach of contract and the NBS should be scrapped
    with the €80m of public and EU spent on something more suitable to the goal of
    delivering broadband to those that are currently not served by broadband.
    Other key contracted road map events such as an increase in MINIMUM data
    speeds for NBS users to 1.6mbits on the 1st of July 2010 and completion of
    the entire roll out to the intended 388 masts (or their replacements)
    by the end of September 2010 will not be met.
    While there have been issues with planning authorities with regard to the
    proposed 160 entirely new masts planned for this scheme (for which one
    feels some sympathy for three) the fact is that fewer than half of the
    160 new masts have been installed to date. In Kerry only 2 masts have
    eceived permission out of the 10 applied for. This scheme is to be
    installed and fully commissioned in less than 5 months. 3 are showing
    no sense of urgency.
    Contract changes are flagged here, please note that NBS customers are
    considered to be “pay monthly”

    http://www.three.ie/terms/customer_notification.htm
    For the record here are the original terms as originally announced:
    http://www.dcenr.gov.ie/Communications/Communications+Development/National+Broadband+Scheme/NBS+FAQs.htm#Limits
    Will there be download and upload limits and what will they be?
    An uncharged monthly data cap of 15GB (12GB download and 3GB upload)
    will apply for the wireless product while 11GB (10GB download and 1GB
    upload) will be available for satellite users.
    Are there plans to upgrade speeds?
    Two upgrades of the wireless product are planned by 3 in the coming
    years without any increase in the monthly recurring charge:
    July 2010 Min (at cell edge) Max (at cell centre)
    Download Speed 1.6Mbps 6.8Mbps
    Upload Speed 1.2Mbps 4Mbps
    Maximum contention ratio of 22:1
    Round-trip latency: 100ms
    October 2012 Min (at cell edge) Max (at cell centre)
    Download Speed 2.3Mbps 10.4Mbps
    Upload Speed 1.4Mbps 4.8Mbps
    Maximum contention ratio of 18:1
    Round-trip latency: 100ms
    Furthermore, since the inception of this scheme they have been
    unable to maintain the initial minimum contracted download of
    1.2Mbps (in common with all Mobile operators), 100ms Latency,
    always on or always connected.
    With W-CDMA/3G/UMTS/HSPA it’s not even possible to have a
    guaranteed minimum connect speed at the cell edge.
    This “distance” will vary depending on the number of simultaneous
    connected users.
    The maximum contention isn’t possible to achieve with mobile
    subscribers. The industry standard is that contention
    is the sum of package speed per user divided by the system
    speed, as if all users connected. It’s not the real time
    number of users per mast. The actual reality is that only a
    certain percentage of customers connect at once,
    thus on a real broadband system you might only see a real
    time reduction of package speed from 8Mbps to
    7.5Mbps due to real time contention. The 12:1, 24:1 or 48:1
    contention rates quoted refer to the bandwidth
    needed by total number of customers, not actual connections.
    Three Themselves maintain that the commonly accepted distances
    for 3g cell sites in varying environments are:
    150m – 350m in urban areas
    800m – 1000m in suburban areas
    2km – 5km in rural areas
    That shows clearly the density of cells required for adequate service
    levels and also why the NBS can never possibly achieve its stated aims.
    If there was a true representative and unbiased audit comparing 3G
    system in areas where the customer sign-ups have reached a mature
    stage, we suggest that the system would not ever have met either
    the NBS specification or met the commonly accepted standards of Broadband.


Comments

  • Registered Users, Registered Users 2 Posts: 1,813 ✭✭✭clohamon


    In Kerry only 2 masts have
    received permission out of the 10 applied for.

    I don't think that's correct.
    Most of the Kerry applications were eventually granted with conditions on appeal to ABP. PM'd you on this.

    Have H3GI confirmed that changes to cap includes NBS?


  • Registered Users, Registered Users 2 Posts: 101 ✭✭IrelandOffline_


    clohamon wrote: »
    I don't think that's correct.
    Most of the Kerry applications were eventually granted with conditions on appeal to ABP. PM'd you on this.

    Have H3GI confirmed that changes to cap includes NBS?

    Thanks for clarifying that about the masts...

    3 have neither confirmed or denied so we are attempting to get clarification on that point.

    One of the most important points (probably missed in the post) was confirmation of the size of the cells required and that cell shrinking also was confirmed by 3.

    To cover an area the size of Kerry would require cell sites every 5 km rather than 10 or so cell sites as granted. This is an important point for coverage in that particular area. It shows that the number of cell sites required to deliver any sort of reasonable midband coverage is enormous.


  • Registered Users, Registered Users 2 Posts: 32,417 ✭✭✭✭watty


    That would really at that be only voice coverage.

    All cell density planning is really based on ensuring a certain high pecentage of voice call attempts succeed. To have the same level of Service for 1.2Mbps would require many more masts. Basically one for approx. every 60 customers assuming about 18:1 contention.


  • Registered Users, Registered Users 2 Posts: 1,813 ✭✭✭clohamon



    One of the most important points (probably missed in the post) was confirmation of the size of the cells required and that cell shrinking also was confirmed by 3.

    To cover an area the size of Kerry would require cell sites every 5 km rather than 10 or so cell sites as granted. This is an important point for coverage in that particular area. It shows that the number of cell sites required to deliver any sort of reasonable midband coverage is enormous.

    That point was well made thanks, but regarding the possible delay.....

    It is not clear whether the 92% hspa/ 8% satellite split applies at the ED, County or National level.

    DCENR
    In recognition of the fact that some areas will be very costly and difficult to reach, in a very limited number of cases, 3 will make available a satellite product of 1Mbps download and 128kbps upload. This will cover up to a maximum of 8% of fixed residences and businesses in the NBS coverage area.

    H3GI
    In recognition of the fact that some areas will be very difficult to reach using standard infrastructure, in a limited number of cases 3 will make available a satellite product, which may cover up to 8% of the NBS areas.

    If its at national level then some EDs or even whole counties might be served predominantly by satellite so long as the correct HSPA/satellite proportions are met at national level.

    AFIK the scheme no longer claims to be ubiquitous in a mobile sense but only has to serve those who request it, within the NBS area; ie its not actually an area based scheme, its a premises based scheme. What's more its also a demand based scheme, so the theoretical catchment is not really relevant. What's important is how many people (premises) actually apply for it and where they are.


    If the take up was sufficiently low in remote areas it may not be necessary to build masts at all and still meet the hspa/satellite ratio for the NBS as a whole. Even completing the planning applications could prove extremely wasteful if demand ultimately turned out to be low. The point is, that if the stated HSPA/satellite ratio is not enforced at the ED level, there is every incentive (late fines aside) to hold off building expensive masts in the remote areas until the very last moment.


  • Banned (with Prison Access) Posts: 25,234 ✭✭✭✭Sponge Bob


    clohamon wrote: »
    It is not clear whether the 92% hspa/ 8% satellite split applies at the ED, County or National level..

    It was quite clear to Damien Gallagher of 3 who is the rollout manager, it was per ED.

    No ED can go live where 92% of the population cannot receive a terrestrial signal. No more than 8% in any given ED can be on satellite.


  • Advertisement
  • Registered Users, Registered Users 2 Posts: 32,417 ✭✭✭✭watty


    If the revenue from voice calls + mast subsidy in an ED doesn't look like that over 5 years would exceed the cost, why would they build?

    I've never thought they would do all ED.

    They don't stand to lose much.

    In fact if they got kicked out of NBS after they do all the masts they are prepared to do, it would suit them fine.


  • Banned (with Prison Access) Posts: 25,234 ✭✭✭✭Sponge Bob


    watty wrote: »
    If the revenue from voice calls + mast subsidy in an ED doesn't look like that over 5 years would exceed the cost, why would they build?
    As they have the only A licence they should make a point in staying ahead in 3g coverage...after all what about the spectrum under 1ghz to be auctioned soon.
    I've never thought they would do all ED.

    I agree, they will abandon c10% of all EDs on grounds of planning difficulty ...they need but apply in sacs and spas :)

    So they pass on €8m of cash, so what.


  • Registered Users, Registered Users 2 Posts: 32,417 ✭✭✭✭watty


    €8m is nothing if you are saving €20m


Advertisement