Advertisement
If you have a new account but are having problems posting or verifying your account, please email us on hello@boards.ie for help. Thanks :)
Hello all! Please ensure that you are posting a new thread or question in the appropriate forum. The Feedback forum is overwhelmed with questions that are having to be moved elsewhere. If you need help to verify your account contact hello@boards.ie
Hi there,
There is an issue with role permissions that is being worked on at the moment.
If you are having trouble with access or permissions on regional forums please post here to get access: https://www.boards.ie/discussion/2058365403/you-do-not-have-permission-for-that#latest

Starting a New Build - What are the Main Items?

  • 24-07-2008 2:08pm
    #1
    Registered Users, Registered Users 2 Posts: 641 ✭✭✭


    I'm considering starting a new build - what would be the main headings to be listed if I'm building a project plan to manage the program?
    Where would I get a good list of required activities for a standard 2-storey block-build with a garden and driveway?


Comments

  • Closed Accounts Posts: 457 ✭✭Leadership


    I started my project plan with these headings, I cannot for the life of me remember the web site I got them off isb*** or something. Its the breakdown of cost for a build but the headings work for my plan.


    Site Clearance
    3%
    Foundation
    9%
    External Walls
    17%
    Roof
    9%
    Windows and External Doors
    7%
    Upper Floor
    2%
    Stairs
    1%
    Internal Walls
    2.50%
    Internal Doors
    2.50%
    Floor Finishes
    4%
    Wall Finishes
    5%
    Ceiling Finishes
    2%
    Heating
    6%
    Electrical Installation
    4%
    Water Installation (Cold/Warm)
    2%
    Waste & Sanitary
    7%
    Kitchen
    5%
    Built In Cupboards
    1%
    Professional Fees
    11%


  • Registered Users, Registered Users 2 Posts: 29,308 ✭✭✭✭Quazzie


    Leadership wrote: »
    I started my project plan with these headings, I cannot for the life of me remember the web site I got them off isb*** or something. Its the breakdown of cost for a build but the headings work for my plan.


    Site Clearance
    3%
    Foundation
    9%
    External Walls
    17%
    Roof
    9%
    Windows and External Doors
    7%
    Upper Floor
    2%
    Stairs
    1%
    Internal Walls
    2.50%
    Internal Doors
    2.50%
    Floor Finishes
    4%
    Wall Finishes
    5%
    Ceiling Finishes
    2%
    Heating
    6%
    Electrical Installation
    4%
    Water Installation (Cold/Warm)
    2%
    Waste & Sanitary
    7%
    Kitchen
    5%
    Built In Cupboards
    1%
    Professional Fees
    11%
    www.Iaosb.ie < loads of very useful information including the above mentioned


  • Registered Users, Registered Users 2 Posts: 46,544 ✭✭✭✭muffler


    There are quite a few threads in this forum if you want to have a root around.


Advertisement